RENCANA ANGGARAN BIAYA (RAB) | ||||||
ENGGINERING ESTIMATE ( EE ) | ||||||
PROGRAM | : PENGEMBANGAN TK-SD KYAI IBRAHIM, SURABAYA | |||||
KEGIATAN | : PEMBANGUNAN GEDUNG TK-SD KYAI IBRAHIM, SURABAYA | |||||
LOKASI | : JL. SIWALANKERTO UTARA NO. 50A, WONOCOLO- SURABAYA | |||||
NO | URAIAN PEKERJAAN | SAT | VOLUME | HARGA SAT | JUMLAH | |
(Rp) | (Rp) | |||||
I | PEKERJAAN PERSIAPAN | |||||
1 | Pembersihan lokasi / Pembongkaran | ls | 1,00 | 500.000,00 | 500.000,00 | |
2 | Pengukuran / Bouwplank | m1 | 50,00 | 35.450,00 | 1.772.500,00 | |
JUMLAH | 2.272.500,00 | |||||
II | PEKERJAAN TANAH | |||||
1 | Galian tanah | m3 | 46,57 | 31.750,00 | 1.478.597,50 | |
2 | Urugan pasir dibawah pondasi dan dibawah lantai | m3 | 20,50 | 102.700,00 | 2.105.350,00 | |
3 | Urugan kembali + perataan galian pondasi | m3 | 13,97 | 10.581,00 | 147.816,57 | |
JUMLAH | 3.731.764,07 | |||||
III | PEKERJAAN COR BETON | |||||
1 | Cor Pondasi Strauss | m3 | 7,56 | 2.000.000,00 | 15.120.000,00 | |
2 | Pondasi Setapak 150x150 dan 100x100 | m3 | 8,75 | 2.600.000,00 | 22.750.000,00 | |
3 | Sloof Utama dan Sloff Pagar | m3 | 9,46 | 3.150.000,00 | 29.786.400,00 | |
4 | Kolom Struktur | m3 | 20,68 | 3.250.000,00 | 67.210.000,00 | |
5 | Kolom Praktis | m1 | 0,66 | 64.500,00 | 42.570,00 | |
6 | Plat dak Lantai Beton T=12 Cm | m3 | 36,53 | 3.550.000,00 | 129.681.500,00 | |
7 | Cor Balok Struktur Lantai | m3 | 30,50 | 3.650.000,00 | 111.325.000,00 | |
8 | Cor Beton Lantai Kerja | m3 | 2,20 | 610.500,00 | 1.343.100,00 | |
9 | Cor Lisplank | m3 | 5,25 | 3.550.000,00 | 18.637.500,00 | |
10 | Cor Tangga Ram | m3 | 4,85 | 3.650.000,00 | 17.702.500,00 | |
JUMLAH | 413.598.570,00 | |||||
IV | PEKERJAAN PASANGAN LANTAI DASAR | |||||
1 | Pasangan batu bata | m2 | 404,49 | 71.978,00 | 29.114.381,22 | |
2 | Plesteran dinding | m2 | 805,74 | 26.296,00 | 21.187.739,04 | |
3 | Acian Dinding | m2 | 805,74 | 14.500,00 | 11.683.230,00 | |
4 | Acian Kolom | m2 | 167,36 | 14.500,00 | 2.426.720,00 | |
5 | Benangan | m1 | 615,60 | 11.500,00 | 7.079.400,00 | |
JUMLAH | 71.491.470,26 | |||||
V | PEKERJAAN PINTU DAN JENDELA DAN PARTISI | |||||
1 | Kusen Pintu Meranti Merah | m1 | 64,00 | 63.000,00 | 4.032.000,00 | |
2 | Kusen Jendela Alumunium | m1 | 256,44 | 80.000,00 | 20.515.200,00 | |
3 | Daun Jendela Nako 8 Daun +Kaca | set | 56,00 | 175.000,00 | 9.800.000,00 | |
4 | Daun Jendela Nako 2 Daun +Kaca | set | 4,00 | 75.000,00 | 300.000,00 | |
5 | Daun Pintu Kayu Jati | set | 12,00 | 350.000,00 | 4.200.000,00 | |
6 | Pintu PVC | set | 3,00 | 200.000,00 | 600.000,00 | |
7 | Kunci pintu 2 kali putar | set | 10,00 | 98.107,00 | 981.070,00 | |
8 | Pegangan Pintu | set | 8,00 | 100.000,00 | 800.000,00 | |
9 | Grendel Tanam | set | 8,00 | 50.000,00 | 400.000,00 | |
10 | Pasang Partisi Rangka Galvalum + Gypsumboard 9 mm | m2 | 121,90 | 130.000,00 | 15.847.000,00 | |
JUMLAH | 57.475.270,000 | |||||
VI | PEKERJAAN PASANGAN KERAMIK DAN PAVING | |||||
1 | Keramik lantai 40/40 Motif Kw 1 | m2 | 389,12 | 95.000,00 | 36.966.400,00 | |
2 | Keramik dinding 20/25 | m2 | 52,40 | 97.000,00 | 5.082.800,00 | |
3 | Keramik lantai Tangga 30x30 | m2 | 40,50 | 94.000,00 | 3.807.000,00 | |
4 | Pekerjaan paving | m2 | 119,00 | 65.000,00 | 7.735.000,00 | |
JUMLAH | 53.591.200,00 | |||||
VII | PEKERJAAN PLAFON,LIST DAN ATAP | |||||
1 | Pasang Gording C150 | Kg | 552,53 | 15.000,00 | 8.287.950,00 | |
2 | Pasang Galvalum | m2 | 180,00 | 40.000,00 | 7.200.000,00 | |
3 | Pasang Plafon Hollow dan Gypsumboard 9 mm | m2 | 190,30 | 80.000,00 | 15.224.000,00 | |
4 | List Plafon | m1 | 575,50 | 11.000,00 | 6.330.500,00 | |
JUMLAH | 37.042.450,00 | |||||
VIII | PEKERJAAN PENGECATAN | |||||
1 | Cat Plafon dan Lisplank | m2 | 645,00 | 15.038,00 | 9.699.510,00 | |
2 | Politur Kusen Dan Pintu | m2 | 55,68 | 25.500,00 | 1.419.840,00 | |
3 | Cat Tembok + Partisi | m2 | 908,94 | 15.038,00 | 13.668.639,72 | |
JUMLAH | 24.787.989,72 | |||||
IX | PEKERJAAN SANITASI AIR | |||||
1 | Talang tegak+ untuk saluran PVC D. 4" | m1 | 96,00 | 42.980,00 | 4.126.080,00 | |
2 | Pipa PVC 3" Ut Saluran Air Kotor | m1 | 42,00 | 37.980,00 | 1.595.160,00 | |
3 | Pipa PVC D. 3/4" untuk air bersih | m1 | 99,00 | 20.480,00 | 2.027.520,00 | |
4 | Bak mandi | bh | 3,00 | 265.450,00 | 796.350,00 | |
5 | Closet jongkok | bh | 3,00 | 321.500,00 | 964.500,00 | |
6 | Avor bak mandi | bh | 3,00 | 10.000,00 | 30.000,00 | |
7 | Kran tembok | bh | 10,00 | 15.000,00 | 150.000,00 | |
8 | Septic Tank | unit | 1,00 | 2.000.000,00 | 2.000.000,00 | |
9 | Resapan untuk WC | unit | 1,00 | 1.500.000,00 | 1.500.000,00 | |
10 | Avor lantai | bh | 6,00 | 20.000,00 | 120.000,00 | |
11 | Tempat cuci piring | bh | 1,00 | 150.000,00 | 150.000,00 | |
12 | Tandon Air Bawah | unit | 1,00 | 6.000.000,00 | 6.000.000,00 | |
JUMLAH | 19.459.610,00 | |||||
X | PEKERJAAN PAGAR | |||||
1 | Pasangan Bata | m2 | 24,02 | 71.978,00 | 1.728.911,56 | |
2 | Plesteran Dinding Pagar | m2 | 48,04 | 26.296,00 | 1.263.259,84 | |
3 | Cat Dinding Pagar | m2 | 48,04 | 15.038,00 | 722.425,52 | |
4 | Pemasangan Pagar dan Pintu Besi | m2 | 44,47 | 430.000,00 | 19.122.100,00 | |
JUMLAH | 22.836.696,92 | |||||
XI | PEKERJAAN INSTALASI LISTRIK | |||||
1 | Titik lampu | ttk | 39,00 | 105.000,00 | 4.095.000,00 | |
2 | Titik Stop Kontak | ttk | 16,00 | 105.000,00 | 1.680.000,00 | |
3 | Lampu SL 14 Watt komplit + pasang | bh | 39,00 | 42.000,00 | 1.638.000,00 | |
4 | Stop kontak + pasang | bh | 16,00 | 20.000,00 | 320.000,00 | |
5 | Skakelar Tunggal + Pasang | bh | 5,00 | 18.500,00 | 92.500,00 | |
6 | Skakelar double + Pasang | bh | 11,00 | 24.500,00 | 269.500,00 | |
7 | Instalasi listrik dan tambah daya | unit | 1,00 | 5.260.000,00 | 5.260.000,00 | |
8 | Pasang MCB 8A | bh | 9,00 | 40.000,00 | 360.000,00 | |
JUMLAH | 13.715.000,00 | |||||
DIBULATKAN MENJADI | JUMLAH SELURUHNYA | 720.002.520,97 | ||||
DIBULATKAN MENJADI | 720.000.000,00 |